Urban Development

Red Sea Global, Shura Island

Red Sea · Saudi Arabia
Red Sea Global, Shura Island

Project Overview

Atlantis Contracting successfully delivered the supply and installation of PROMATECT®-H passive fire protection systems for the Red Sea Global Shura Island Infrastructure Development, one of Saudi Arabia's major Vision 2030 giga-projects.

The scope focused on fire-rated shaft closures and fire compartmentation, protecting vertical and horizontal MEP shafts, service risers, and critical building interfaces. PROMATECT®-H calcium silicate fire protection boards were used to establish and maintain fire-rated barriers, helping prevent the spread of fire, smoke, and hot gases between building compartments.

The works were executed across multiple building and infrastructure zones, with shaft configurations and fire-resistance requirements tailored to the specific project conditions and approved fire protection designs.

  • Location: Shura Island, Red Sea, Saudi Arabia
  • Client: Al Tamimi Contracting Company
  • End Client: Red Sea Global
  • Contractor: Atlantis Contracting
  • Completion: 2023
  • Scope: Supply & Installation of Passive Fire Protection Systems
  • Main System: PROMATECT®-H Calcium Silicate Fire Protection Board
  • Fire Rating: Up to 2 & 4 Hours, subject to approved system design

Scope of Works

  1. Supply and installation of PROMATECT®-H fire protection boards.
  2. Construction of fire-rated MEP shaft enclosures.
  3. Protection of vertical service shafts and risers.
  4. Fire-rated closures around electrical, mechanical, and plumbing service zones.
  5. Installation of galvanized steel supporting frameworks.
  6. Firestopping of board joints and interfaces.
  7. Sealing of service penetrations through fire-rated shaft walls.
  8. Coordination with structural, MEP, and fit-out works.
  9. Inspection, quality control, and project documentation.

Key Challenges & Solutions

Complex Shaft Configurations

Different building typologies and service requirements resulted in varying shaft dimensions, interfaces, and fire-resistance requirements.

Atlantis Solution:

Atlantis developed installation details according to the specific shaft configuration and approved fire-rated system requirements, including customized galvanized steel supporting frameworks.

Multi-Trade Coordination

MEP, civil, and fit-out activities were progressing concurrently, requiring shaft closures to be carefully coordinated with other trades.

Atlantis Solution:

A formal shaft readiness process was implemented to ensure MEP services were completed and approved before shaft closures commenced. Installation teams were then redirected to ready zones to maintain project progress.

Quality & Compliance

The project required stringent inspection, material traceability, and documentation standards consistent with a major Red Sea Global development.

Atlantis Solution:

Atlantis maintained comprehensive quality documentation, including product data, fire test documentation, method statements, material records, and inspection sign-offs for completed installations.

Main System – PROMATECT®-H

  • Material: Non-combustible calcium silicate fire protection board
  • Application: Fire-rated shaft enclosures, service risers, MEP shafts, and compartmentation
  • Fire Rating: Up to 2 and 4 hours, according to approved system design
  • Supporting Structure: Galvanized steel framing
  • Key Properties: High fire resistance, dimensional stability, moisture resistance, and impact resistance

Project Execution

  • The project was delivered through a controlled process covering:
  • Site mobilization and detailed shaft surveys.
  • Assessment of shaft readiness and construction interfaces.
  • Material procurement and controlled on-site storage.
  • Fabrication and installation of galvanized steel supporting frameworks.
  • Installation of PROMATECT®-H fire-rated shaft enclosures.
  • Firestopping of joints, interfaces, and service penetrations.
  • Inspection and quality verification.
  • Documentation and material traceability.
  • Final inspection and project handover.

Project Outcome

Atlantis Contracting successfully delivered the passive fire protection works for the Shura Island Infrastructure Development, providing fire-rated shaft closures and compartmentation systems designed to maintain the integrity of critical fire barriers.

The completed PROMATECT®-H systems contribute to the project's overall fire safety strategy by protecting MEP service zones and helping limit the spread of fire, smoke, and hot gases between building compartments.

The project demonstrates Atlantis Contracting's capability in delivering high-specification passive fire protection systems for major Saudi giga-projects, combining specialist installation, technical coordination, quality control, and project-specific fire-rated solutions.